The two failure modes we see most often are a mounting that does not fit the hull as drawn, and a power or data interface that nobody verified on board. Both are avoidable with a short information pack exchanged before mobilisation.
A complete pack answers these:
- Vessel particulars: hull form, draft at the intended mounting station, deadrise, and whether the location is forward of propeller wash.
- Mounting arrangement: through-hull, over-the-side pole, or temporary frame; who supplies the fairing, the flange and the cable gland.
- Services on board: available DC voltage and current, UPS or clean supply, network or serial ports, and the NMEA or Ethernet destination.
- Site conditions: depth range, expected current speeds, sediment type, salinity, and any dredging or construction activity during the survey.
- Access and schedule: yard dates, diver or ROV availability, and the acceptance criteria for the installation.
Send this before the mobilisation date and the installation becomes a scheduled task instead of a site problem. Questions specific to your vessel can be posted here or sent through the contact page.